Our process

From layout to ready-to-use.

Six controlled steps — the longest build phase happens in our factory, keeping site work and disruption to a minimum.

1

Planning

We build our planning on your brief, layout or concept — partnering with local planning firms to deliver a complete, code-compliant design.

  • Architecture — design & layout
  • Structural — load-bearing engineering
  • Fire protection — safety & compliance
  • Building services — MEP & technical systems
2

Manufacturing & Trial Assembly

All modules are produced in our facility and pre-assembled as a complete trial build under controlled conditions.

  • Steel frame — fabricated to spec & approved planning
  • Concrete floors — poured and integrated to eliminate vibration
  • Interior finish — fitted in-factory to cut on-site time
  • Technical room & AHU — prefabricated complete with ducting
3

Quality Control I — In-Factory

Every module is verified against all technical and hygienic standards before release.

  • Electrical — wiring and systems fully tested
  • Sanitary — plumbing and water systems verified
  • Hygiene — medical-grade standards confirmed
  • Stage gates — every step signed off before the next department
4

Delivery

Finished modules ship to site on a precise schedule — sized to your project and routed for the best balance of time and cost.

  • Standard units — 4.3 m wide · 4.2 m high · up to 10 m long
  • Custom sizes — smaller modules to match requirements
  • Two production hubs — the Netherlands and Lithuania
  • Ferry & truck — combined transport saves time and cost
5

Assembly & Commissioning

On-site assembly is deliberately short — crane-mounted in a short assembly window, followed by interior fit-out and commissioning.

  • 1–2 weeks — typical crane assembly for small to large buildings
  • 8–12 fitters — a compact crew on site at any one time
  • Short closures — surrounding areas blocked only briefly
  • Built in the works — short site time saves cost and avoids delays
6

Quality Control II — On-Site

On site, every system is verified once more — confirming the facility meets all medical and regulatory standards before handover.

  • Electrical & sanitary — re-inspected in place
  • Ventilation — air handling verified in operation
  • Hygiene testing — contact-plate sampling and particle measurement
  • Expert sign-off — all required statutory acceptance inspections

Ready to use

All six steps complete — your facility is delivered fully tested, certified and ready for immediate medical use.

  • Fully certified — all inspections and approvals passed
  • Turnkey handover — operational from day one
  • Built for medical use — durable, compliant modular construction

Together we realise your clinic project — modular, turnkey and in just 190 days.